WEED BEACH IMPROVEMENT PROJECT UPDATE:
Project pictures (video)
Project pictures (updated January 18, 2012)

Framing, roof, windows complete on paddle tennis building
Framing for new bathhouse and gazebo completed, roof to be completed in late January
Project completion expected in mid-late April 2012

Although not closed to the public, please use caution in this playground area during this work.

Parking at Weed Beach will be limited during construction


Weed Beach Site Plan

Mobilization Plan

Weed Beach Plan Introduction

Weed Beach Master Plan (9MB)

Weed Beach Building Committee Charge approved Sept. 20, 2006